Linking tasks
complete
M
Mark Doyle
Functionality needed for linking card tasks to allow revisions on the fly. Using footings as a simple example. To make a footing requires Concrete delivery, Pour Date, Form work and rebar. Can we link these tasks in a sequence. Now if the are in sequence, if I drag a footing card from week 2 to week 6, it would also move the linked cards. Otherwise we would have to manually move each card to the next week.
Clive Jordan
marked this post as
complete
Now dependencies update task dates in the Timeline View:
Photo Viewer
View photos in a modal
Clive Jordan
Dependancies are added already but we are now looking to add a critical path that moves the downstream tasks too 👍